NHS England – Creating Commercial Contract Management Control Across a National Supplier Portfolio
Is our organisation exposed because contract obligations, changes and decisions are not consistently documented?

“Maintaining commercial control and contractual compliance on our NEC3 project has become increasingly difficult.”
Discover how Clear implemented disciplined NEC3 governance and change control to restore commercial stability.
A major programme to replace security intercom systems across 40 multi-storey social housing blocks in Sunderland was underway under an NEC3 Option B contract between the Housing Association and the supplier, with an external project management firm acting for the Housing Association.
The supplier required support to establish disciplined NEC3 contract administration, manage change effectively and strengthen governance across the programme to ensure delivery was commercially viable and operationally controlled.
Contract Administration and Governance
Change and Risk Management
Programme and Supplier Management
Having worked with the Clear team on a significant project over the past 12 months, they shared considerable experience to effectively manage the commercial aspects of the programme while developing our internal capability for future work. Their calm, structured and commercially focused approach added real value.